RIBA Plan of Work Stages Explained

Posted on: 25 November 2026


Our Guide to the RIBA Plan Of Work


The RIBA stages are the eight stages, numbered 0 to 7, that the RIBA Plan of Work uses to divide a building project, from the first decision to build through to the life of the finished building. Most UK architects organise their fee proposals and drawings around them, so the stage numbers tend to come up early in any conversation about a new home or a residential project. This article explains what happens at each stage, and also covers what a list of stage descriptions usually leaves out: where the stages overlap, where a project tends to pause for planning, and what you as the client are asked to decide along the way. If you want to see how it lines up with the way we run projects, our process sets out the steps.

Riba Chartered Architects

 



What the RIBA Plan of Work Is, And What It Is Not


The RIBA Plan of Work, often shortened to PoW, is a framework published by the Royal Institute of British Architects. It was introduced in 1963 to give architects and clients a shared way of describing the stages of a project. It was overhauled in 2013, when Stage 0 and Stage 7 were added, and updated again in 2020. The current version, the stage template and the supporting guidance are free to download from the RIBA Plan of Work page.

Where people often go wrong is in what kind of document it is. The Plan of Work describes what each stage should achieve. It doesn’t say who carries out each task, what anything costs or how long a stage lasts, and the RIBA says plainly that it is not a contractual document. Those details belong in the appointment you agree with your architect and, later, in the building contract with your builder. What the stages give everyone is a common reference, so when an engineer describes a drawing as Stage 3 information, the rest of the team knows roughly how far the design has developed.

The framework is also procurement neutral. It works whether the builder is appointed by tender once the design is finished or brought in earlier under design and build. That choice moves some events around, which we come back to further down.


The Eight RIBA Stages at a Glance


Stages 0 and 1 are the client’s preparation before any design begins. Stages 2, 3 and 4 are the RIBA design stages. Stages 5 to 7 cover the build, the handover and the life of the building. In the usual sense of the word, a project runs from Stage 1 to Stage 6: Stage 0 may end in a decision not to build at all, and Stage 7 continues for as long as the building is in use. Although its called Stage 7, it is the 8th step.

Our stepRIBA stagesWhat you see
1. Survey, Brief and Development0 and 1Measured survey and existing drawings, a brief workshop, a written brief and a plan with milestones
2. Design and Planning2 and 3Concept options, sketches and 3D visuals, a coordinated planning pack, the planning process managed through to a decision
3. Building Regulations and Technical Design4Detailed drawings and specifications, consultants appointed and coordinated, the building regulations application
4. Tender and Contractor Selection4The tender pack, builders’ returns compared, advice on the form of contract, the signed building contract
5. Construction and Handover5 and 6, with post-completion support into 7Site inspections and progress updates, contract administration, practical completion, the defects period, handover with certificates and manuals

The 0-7 RIBA Stages Explained


RIBA Stage 0: Strategic Definition

Stage 0 is where a client works out whether a building project is the best way to meet their needs in the first place. The RIBA treats it as strategic work rather than design, and its own guidance uses the example of an organisation that needs more space weighing up better use of its existing premises against an extension or a new building. A homeowner faces a smaller version of the same choice: whether to extend, remodel what is already there, or move. On residential projects this stage is often short and informal, sometimes no more than a first conversation, but it is where the scope of the project is first decided.

RIBA Stage 1: Preparation and Briefing

A project brief sets out what the building has to do. It covers the rooms and spaces you need and how they relate to each other, the quality you are aiming for, the budget and programme, and the outcomes you want from the finished building, including sustainability targets such as energy performance. Stage 1 pulls all of this together and checks that it fits on the site. It ends when you approve the brief.

Feasibility studies happen here, though the RIBA counts them as part of briefing and not as the start of design. Their job is to test whether what you want will fit and is likely to be acceptable, without yet choosing between options. Site information is collected at the same time. On a new build that often means a topographical survey of the plot, and on an existing house a measured survey of the building. Pre-application planning advice is sought where it is needed.

The RIBA template says no design team is required for Stages 0 and 1. In practice, on most residential projects the architect is appointed at this point to carry out the survey and help shape the brief, which the RIBA’s guidance accepts on smaller projects, and it is how the first step of our own process works. One problem the RIBA singles out is a brief that is rushed so that design can start sooner. In our experience that tends to lead to extra rounds of design later on, because questions the brief should have answered end up being settled by redrawing.

If you want a low-energy home, Stage 1 is the time to say so. The 2020 Plan of Work expects sustainability outcomes to be agreed in the brief and checked again once the building is in use, and the RIBA now publishes a Passivhaus overlay for projects working to that standard. Our eco architecture work starts from this point in the brief.

RIBA Stage 2: Concept Design

Design begins at Stage 2. The architectural concept is the overall idea for the building: how it sits on the site, how the main spaces are arranged, its form and character, and the broad approach to structure and services. It is usually developed as a few options, reviewed with you, and narrowed down to one.

The RIBA describes the brief as staying live during this stage. Developing the design often shows that something in the brief doesn’t work as written, or that there is a better answer than the one first asked for, and the brief is adjusted to suit. Those adjustments are recorded and agreed so that everyone is working to the same version.

Pre-application advice from the planning authority is usually obtained during Stage 2, and the route to building regulations compliance is agreed. On some sites an outline planning application is made at this point. A cost plan is prepared alongside the design so that the concept can be checked against the budget.

The stage ends with you signing off the concept. The RIBA’s guidance is firm that the concept should be settled here and should not keep changing once Stage 3 begins, because Stage 3 builds the engineering around it. Moving rooms or reshaping a roof after that point means redoing coordinated work, and it is one of the more common sources of delay we see.

RIBA Stage 3: Spatial Coordination

RIBA Stage 3 is the stage at which the architectural design and the engineering design, including structure, drainage, heating, ventilation and electrics, are worked through together until they fit. Spatial coordination is the RIBA’s term for this: beams that clear the window heads, ductwork with a route to run along, a staircase that works with the structure around it. Before 2020 the stage was called Developed Design, and you will still see that name in older documents.

The aim is a design that needs no more than minor changes once technical design starts. Input from specialist consultants, such as fire safety, acoustics or energy, is mostly concluded by the end of the stage so that it can be built into the technical drawings and not added afterwards. Change control also starts here. From this point a change to the agreed design is recorded, and its effect on the programme and the cost plan is understood before it is accepted.

The full planning application is normally based on Stage 3 information. The planning note in the RIBA Plan of Work 2020 Overview says applications are generally submitted at the end of Stage 3, and should only go in earlier once there is enough information to support them. Some clients apply sooner to get an answer sooner. The RIBA recommends that only for experienced clients who understand the risks, the main one being that an approved scheme may then need changing once the engineering is resolved, and changes after approval can mean a further application.

For a listed building or a house in a conservation area, listed building consent usually runs alongside the planning application. The conservation officer may ask for more detail at this stage than a standard application would need, such as window and door sections or the specification of materials. We have written separately about what can be changed in a Grade II listed building, and the Plan of Work includes a Conservation Strategy setting out tasks at each stage for projects involving listed and historic buildings.

Once the application is submitted, the project often pauses. Technical design carried out before a decision may need redoing if the planning outcome changes the scheme, so many clients choose to wait for the decision before committing to Stage 4.

RIBA Stage 4: Technical Design

Stage 4 produces the information a builder needs to price and build the project: detailed drawings, specifications for materials, fittings and finishes, structural drawings and calculations, and the services design. The exact brick, roof covering, window system and floor finishes are chosen at this stage, so it is often where clients spend the most time making decisions.

The building regulations application is submitted during Stage 4, and pre-commencement planning conditions, such as approval of material samples, are discharged before work starts on site. Health and safety planning under the CDM Regulations also comes into focus, with a construction phase plan prepared and, where a project meets the threshold, the work notified to the Health and Safety Executive.

The tender and the building contract sit in Stage 4 as well. On a traditional project, which is how our own process is set up, the design is substantially complete before the builder is chosen, so tenders are priced on full information and can be compared on equal terms. You then choose the contractor and sign the building contract, usually with your architect’s advice on which form of contract suits the project.

Stage 4 overlaps with Stage 5 on most projects, which surprises people who expect the stages to run in a straight line. Specialist suppliers, such as a glazing or staircase manufacturer, often produce their own detailed design after they are appointed, and the RIBA places that work in Stage 4 even when it happens while building is under way. Its guidance is clear that design should not drift into the construction stage, because decisions made on site tend to be hurried and are harder to undo.

RIBA Stage 5: Manufacturing and Construction

RIBA Stage 5 is the construction stage. It begins when the contractor is given possession of the site and ends at practical completion, the point at which the building is finished enough to be handed over and occupied, with only minor defects outstanding. The 2020 name includes manufacturing because more of a building is now made off site, from timber frames to complete bathroom pods, and that manufacture belongs to the same stage.

There is no design work in Stage 5 apart from answering site queries. What the architect does depends on the appointment, but it usually includes regular site inspections and responding to questions from the builder. Where the architect acts as contract administrator, it also includes issuing instructions for changes, certifying valuations so the builder is paid for work completed, and certifying practical completion.

Preparation for handover begins before the stage ends. Heating, ventilation and controls are commissioned and tested, and a building manual is put together with the information you will need to run and maintain the house.

RIBA Stage 6: Handover

Stage 6 starts with handover immediately after practical completion and ends at the end of the defects period set in the building contract. During that period the contractor has to put right defects that appear, such as cracking as new plaster dries out, a door that sticks or a joint that leaks, though not ordinary wear and tear. When the period ends, any remaining defects are made good and the final certificate is issued, which concludes the building contract.

The RIBA also includes a review of how the project went and a light-touch post occupancy evaluation. On a house, that mostly means checking that the building is working as intended once you have lived in it for a while, and adjusting systems such as heating controls as the seasons change. Many clients don’t realise this stage exists, and knowing it is coming makes the first year in a new or altered home easier to judge. Under the RIBA’s guidance the design team’s work normally ends here, and anything beyond it needs a separate appointment.

RIBA Stage 7: Use

Stage 7 covers the building in use. It begins at the same time as Stage 6 and runs for the rest of the building’s life. This is where the outcomes set in the brief, including any sustainability targets, are compared with how the building actually performs, through a fuller post occupancy evaluation if one has been commissioned. For a home, that might mean comparing energy use with what was predicted at design stage. The Plan of Work treats Stage 7 as the link back to the beginning: when a building no longer meets its owner’s needs, deciding what to do with it is a new Stage 0.

How the Stages Overlap, Pause and Change with the Procurement Route

Most diagrams of the RIBA stages show eight equal blocks in a row, and real projects rarely look like that. The RIBA’s own stage boundaries are more specific. Stages 0 to 4 generally run one after the other. Stages 4 and 5 overlap on most projects. Stage 5 starts when the contractor is given possession of the site and ends at practical completion. Stage 6 runs from handover to the end of the defects period, and Stage 7 starts alongside Stage 6 and continues for the life of the building.

On a typical residential project, the most noticeable break comes after Stage 3, when the planning application is submitted, and design work largely stops while the local authority decides it. How long that lasts depends on the authority and the scheme, and listed building consent or conditions attached to an approval can add to it. Clients sometimes ask whether technical design can carry on in the meantime. It can, but anything drawn before the decision may need redoing if the scheme has to change, so it comes down to how confident everyone is about the outcome.

The procurement route changes when the builder joins the team. Under traditional procurement, the design is completed through Stage 4, the project is tendered, and the contractor is appointed before Stage 5. Under design and build, the client’s team develops the design to an agreed point, usually somewhere in Stage 3 or early in Stage 4, and the contractor becomes responsible for completing it. In a two-stage version, a contractor is brought in earlier under a pre-construction agreement, and the main contract is signed later. Design and build usually brings the contractor’s input in sooner, while traditional procurement leaves more of the design detail with the client’s own team. Neither route changes what each stage has to achieve, only who does the work and when the contract is signed.

What changed in the RIBA Plan of Work 2020

The 2020 edition kept the eight numbered stages from 2013 and renamed several of them. Stage 1 went from Preparation and Brief to Preparation and Briefing, Stage 3 from Developed Design to Spatial Coordination, Stage 5 from Construction to Manufacturing and Construction, Stage 6 from Handover and Close Out to Handover, and Stage 7 from In Use to Use. Stages 0, 2 and 4 kept their names. Before 2013 the stages were lettered A to L, which is why older drawings sometimes refer to Stage E or Stage F.

The larger changes were in the guidance. Sustainability outcomes are now set in the brief at Stage 1 and checked at Stages 6 and 7. A Plan for Use strategy, the RIBA’s version of the Soft Landings approach, was added to improve handover and aftercare. There is more detail on planning, procurement and the information to be produced at each stage, and since 2020 the RIBA has published overlays on Passivhaus, inclusive design, security, engagement, smart buildings and design for manufacture and assembly. The 2020 template has no sub-stages, so labels such as Stage 4a are an individual practice’s subdivision and not part of the RIBA framework.


Talk To Local RIBA Architects in North Yorkshire


If you are at the start of a project, which stage you are in matters less than having the brief and the site properly understood before design begins. Many of the problems the RIBA describes in its guidance go back to something skipped or hurried early on. If you would like to talk through a project in Harrogate, York, Leeds or elsewhere in Yorkshire, send us your brief and we will come back to you.

Contact Us

We'd love to hear
from you


Get in touch for general enquiries such as planning permission and construction budgets or send us your brief in more detail and we'll get back to you.

GET IN TOUCH

BRIEF US
Harrogate
01423 505 924
10 North Park Road,
Harrogate, North Yorkshire, HG1 5PG
York
01904 217190
152-154 Holgate Road,
York, North Yorkshire, YO24 4DQ